Construction Updates on Vaibhav Vasind Hills

Construction at Vaibhav Vasind Hills started in April 2014 with a “Grand Ground Breaking Ceremony” held at project site attended by our existing customers and esteemed guests. Vaibhav-Vasind Hills has 7 G+4 blocks – E1, E2, E3, G1, G2, G3, and F1, and 1 G+3 block H1. Construction of each block can be divided broadly in four stages:

  • Excavation –  Excavation is completed for G3 block.  E3 and E2 blocks excavation will start shortly.
  • Sub-structure (grade slab),
  • Super-structure (ground floor to terrace), and Finishing (water proofing, tiles, kitchen works, lifts, etc.).

Vaibhav Vasind Hills Roads

Road work started in April 2014 and is running at a smooth pace.

Vaibhav Vasind Hills Buildings

Here are the individual Block wise updates:

  • E3 Block (Excavation) – Surveying is completed, Excavation will start shortly.
  • E2 Block (Excavation) – Surveying is completed, Excavation will start shortly.
  • G3 Block (Excavation) – Excavation is completed, Foundation work in progress.

Other Infrastructures

  • Road work – Started in April 2014.
  • Shopping Complex — Foundation work in progress.

Vaibhav Vasind Hills Model Apartments

Fully furnished model apartments are ready and we encourage you to come and visit it and interact with us on-site.

Construction Updates on Vaibhav Palghar Greens

Construction at Vaibhav-Palghar Greens project started in April 2014 and has been going at a smooth pace. Vaibhav-Palghar Greens has 8 G+4 blocks – Ax1, Ax2, Ax3, Ax4, Ax5, Ax6, C1 and D1.

Construction of each block can be divided broadly in four stages: Excavation, Sub-structure (grade slab), Super-structure (ground floor to terrace), and Finishing (water proofing, tiles, kitchen works, lifts, etc.). Excavation is completed for Ax2 block and C1 blocks.

Vaibhav Palghar Roads

The main arterial road till Vaibhav Palghar Greens is complete and is open for vehicular traffic movements. Internal road work started in April 2014 and is on-going at a smooth pace.

  • Internal road work – Road laying work is in progress till C1 Block.
  • Main Road – Road is completed till entrance of Vaibhav Palghar Greens project.

Vaibhav Palghar Buildings

Here are the individual Block wise updates:

  • Ax1 Block (Excavation) – Excavation completed, foundation work will start shortly.
  • Ax2 Block (Excavation) – Excavation completed, foundation work is in progress.
  • C1 Block   (Excavation) – Excavation completed, foundation work is in progress.

Vaibhav Palghar Model Apartments

Fully furnished model apartments are ready and we encourage you to come and visit it and interact with us on-site.

Construction Updates on VBHC’s Vaibhav Palghar

Construction at Vaibhav-Palghar project started in early 2013 and has been going at a smooth pace. There were initial delays due to heavier than expected monsoon season; however, now project is getting in progress as per schedule. Vaibhav-Palghar has 8 G+4 blocks – A1, A2, A3, A4, A5, A6, A7, and B1.

Construction of each block can be divided broadly in four stages:

  • Excavation,
  • Sub-structure (grade slab),
  • Super-structure (ground floor to terrace), and Finishing (water proofing, tiles, kitchen works, lifts, etc.).

Click here to view more

We have completed  excavation and Sub-structure (grade slab) on all blocks.  Super-structure is completed for A1, A2, A3, A5, A7, and B1 blocks and is on-going for A4 and A6 blocks.

VBHC PALGHAR ROADS

The main arterial road is completed and is open for vehicular traffic movements. Internal road work was scheduled to be completed by end of June. However, due to heavy monsoon season, there has been some delay in completing the internal road as per plan. We plan to complete the internal road networks by end of May 2014.

VBHC PALGHAR BUILDINGS

There has been steady progress in getting the sub-structure and super-structure work in place for all the blocks. Here are the individual Block wise updates:

  1. A1 Block (Superstructure) – Fourth floor completed, finishing works in progress.
  2. A2 Block (Substructure) – Fourth floor completed, finishing work in progress.
  3. A3 Block (Finishing) – Fourth floor completed. Finishing works in progress.
  4. A4 Block (Substructure) – Fourth floor in progress.
  5. A5 Block (Superstructure) – Fourth floor completed, finishing works in progress.
  6. A6 Block (Substructure) – Second floor in progress.
  7. A7 Block (Superstructure) – Fourth floor completed, finishing works in progress.
  8. B1 Block (Superstructure) – Fourth floor complete, finishing works in progress.

VBHC Palghar Other Infrastructures

  1. Internal road work – Nearing completion.
  2. Main Road – Completed.
  3. UG Sump – Construction of structure completed and internal fitting work in progress.
  4. STP – Construction of structure is in progress

VBHC Palghar Model Apartments

Fully furnished model apartments are ready and we encourage you to come and visit it and interact with us on-site.

Update on VBHC’s Vaibhav Bhiwadi

 

Click here to view more

Click here to view more

Bhiwadi has transformed into one of the most sought after real estate markets in recent past. VBHC is developing projects comprising of plots of various sizes sprawling over about 19 acres of land to cater to this demand. It is designed to be a self sustainable community with the provision for all the required amenities and infrastructure.

All necessary approvals from Urban Improvement Trust (UIT), which is a single window clearance body at Rajasthan, have been obtained and construction is almost over. (Please click on the images to view our gallery)

VBHC Bhiwadi TIMELINE

We are almost nearing the completion of the project with all facilities and infra work in their finishing stages. We plan to start offering possession to our customers in the mid of this month (July).

VBHC Bhiwadi CONSTRUCTION PROCESS

The construction activity for plotted development can be majorly categorised as following

  • Laying water supply
  • Laying sewage channels
  • Laying road networks
  • Electricity connections
  • Landscaping and Facility Development
  • Installing sewage treatment plant
  • Installing water treatment plant
  • Installing overhead tanks

VBHC Bhiwadi DETAILED CONSTRUCTION UPDATE

  • The external infrastructure development process is currently near completion. Sewage work, water supply network, storm water channel work are already completed.
  • Road work (GSB and WBM layer & top layer) are also completed.
  • Street light pole erection and other electrical works is 100% completed.
  • Construction for STP, Overhead Tank, and Water Treatment Plant is completed. Tank installation on Over Head Tank structure is going on.

COMPLETION TABLE

ACTIVITY % COMPLETION
Sewage work 100% complete
Water supply 100% complete
Road work GSB 100% complete
Road Work WBM 100% Complete
UGT & WTP Structure 100 % complete. Machinery Installation 100% complete
STP Structure 100 % complete. Pump Installation 100% complete
OHT Structure 100 % complete. Tank installation in process
Storm water drain 100% Complete
Street lighting 100% Complete
Other Electrical works 90% Complete